Picking up
speed
Richard Boddington and Simon Luby
examine how trends in wind farm financing
have evolved as the market has entered
the mainstream
The past 12 months have seen a number
of high-profile acquisitions within
the wind energy industry, and project financing
of wind farms continues to set new precedents.
There is no doubt that wind is now in
the mainstream of the finance world, but how
has it got there, and where will it go next?
The early pioneer projects of the late
1980s and early 1990s were almost universally
developed by utilities that were able to finance
them directly from their balance sheets. This
remained the predominant model for some
years, as financial institutions viewed wind as a
niche market with deal values that were too
small and unfamiliar risk issues that they were
not comfortable with.
Through the 1990s and the early years of
this century, a few banks developed teams specialising
in financing renewable projects to support
emerging non-utility wind farm developers,
but these teams were few and far between.
Financing was generally done on a project-byproject
basis and, with relatively limited competition,
lenders could afford to be cautious,
demanding:
all the consents required to construct the
project be in place before financing;
a significant wind measurement campaign on
the wind farm site, typically for at least one
year;
simple construction contract structures – ie,
an EPC (engineer-procure-construct) wrap,
ensuring all construction risk could be simply
placed on one EPC contractor (typically the
turbine supplier);
turbine warranties extending for a significant
period, typically five years;
long-term power purchase agreements
(PPAs) to remove energy price risk over the
debt period; and
relatively high debt service cover ratios to
cover any remaining uncertainty and risk, traditionally
based on the P90 revenue stream (ie,
the annual output value which there is a 90%
chance of exceeding on average).
However, over the past few years there
have been a number of significant changes in
the wind energy markets, which have driven a
number of trends in wind farm financing.
At the most general level, the increased
focus on climate change and security of energy
supply has seen a significant increase in public
and political support for renewable energy. This
has led to increased confidence in the support
mechanisms put in place, whether these are via
tax credits, fixed tariffs or green certificates.
Against this general background, the rate of
wind farm construction has accelerated rapidly
and this trend is set to continue. In 2000,
approximately 4GW of wind farms were
installed globally. Last year, 20GW of capacity
was installed, equating to approximately $42
billion of investment. Current predictions for
2010 are sitting at around 40GW of installed
capacity.
Impressive as these headline numbers are,
this does not mean that the wind energy market
is trouble-free. Its rapid expansion has
resulted in severe constraints in the turbine
supply market, with installation of new projects
often delayed by waiting times of approximately
two years. This shortage of turbines is also
being reflected in their increasing cost. While
suppliers are working to increase their manufacturing
capacities, they in turn are constrained
by the availability of key components
such as gearboxes and bearings, so it seems
likely that supply constraints will continue for
some time to come.
Problems associated with obtaining planning consent continue to be a significant issue
in some countries. In the UK, for example, only
62% of planning applications were approved in
2007. There is a general feeling in the UK that
government policy to support the development
of renewable energy projects is not
reflected in the local planning system, and it is
often hard to predict whether a project will
successfully negotiate the planning hurdle.
Many markets also suffer from a lack of
suitable grid infrastructure, which can lead to
severe delays in constructing and connecting
otherwise viable wind farm projects. Scotland
is a good example, with a north-south highvoltage
line required to reinforce the grid system.
The permitting and construction of this
line is significantly delayed, leaving an estimated
8GW of potential wind farms sitting in a connection
queue, with connection dates out as
far as 2016.
Lastly, the support mechanisms in place
vary significantly from country to country and
each present their own risks in terms of reliable
revenue forecasting. The US support
mechanism is based on a production tax credit
(PTC), and this mechanism is currently
renewed (or not) every two or three years,
meaning that there is always a risk that the
construction of a project will be delayed and
may therefore not qualify for PTCs. This has
resulted in a wind industry that goes hot and
cold, depending on where it is in the PTC cycle.
In the UK, the support mechanism is
through Renewable Obligation Certificates
(ROCs). The value of this support is dependent
on the amount of capacity installed against
annual targets, so that the value of ROCs will
decrease the closer the UK gets to meeting its
targets. ROC values are currently high, but
there is uncertainty about how they will hold up in the future. In addition, the ROC mechanism
is guaranteed to 2027, with support
mechanism uncertainty beyond this date.
Although this is beyond most current debt
terms, it is beginning to become an issue, particularly
for offshore projects with later commissioning
dates and longer debt terms.
Future uncertainty on support mechanisms
such as the ROC and the PTC is also a
key issue when valuing large portfolios of wind
projects, much of which may still be in early
stages of development. Some of these projects
may not be built for some time, and therefore
their value is very sensitive to future changes
to support mechanisms.
All of the issues above have put a
higher value on projects that are
operational, and many utilities,
operators and investors have been
looking to expand their wind assets by acquiring
wind farm portfolios. These portfolios may
be entirely operational or may contain a spread
of projects that are operational, in construction
and in development.
Last year, we acted as technical adviser in
the acquisition of 33% of the Zephyr/Beaufort
portfolio developed by Npower renewables.
The investment in this 391MW portfolio of
fully operational UK sites was made by
Infracapital, and valued the portfolio at around
£440 million (then around $880 million), giving
a value of approximately £1.1 million per MW.
This value is very much in line with 2007 estimates
of wind farm development and construction
costs and so may seem low for an
operational portfolio. However, the portfolio
includes a number of sites constructed in the
early- to mid-1990s using small turbines which
would now be considered obsolete. In these
cases, much of the value is in the potential for
repowering the sites – a difficult judgement in
today’s volatile planning regime.
More recently, we advised Scottish and
Southern Energy (SSE) in its 2008 purchase of
Irish developer Airtricity. This £1.1 billion deal
added 372MW of operational sites to SSE’s
portfolio, plus a further 9000MW pipeline in
Scotland, Ireland, Portugal and China. This
acquisition was of huge strategic importance to
SSE, allowing it a shortcut to operational sites
and also to a pipeline of wind turbines through
the framework agreements already put in place
by Airtricity.
Offshore wind farms, like early onshore
projects, were originally the preserve of utilities
able to fund off-balance sheet. Despite a
more reliable wind regime offshore, the higher
capital costs and unfamiliar risks associated
with construction and operation of offshore
assets meant that for some time offshore was
not ‘bankable’.
The situation changed in October 2006
when Dexia, Rabobank and BNP Paribas closed
the €189 million (then $238 million) financing
of the 120MW Q7 project off the Dutch coast
– the world’s first project-financed offshore
project. SgurrEnergy took a technical due diligence
role in this deal, and has provided similar
support in the financing of the Thornton Bank, Thanet and Ormonde offshore wind farms.
Q7 was originally expected to be a relatively
simple entry into offshore wind project
finance, with a single EPC contract provided by
turbine-maker Vestas. However, this initial contract
structure failed and the project was constructed
under two contracts, with Vestas and
marine contractor Van Oord. The banks also
agreed to share the construction risks, with
contingencies for construction delay shared
equally by the developer and the banks.
Subsequent offshore projects are now
being financed based on similar models, with
the next step likely to be the financing of offshore
portfolios and development pipelines.
From a financing point of view, the changing
market has led to a rapid evolution of
strategies. The constraints in turbine supply and
the maturation of wind farm financing has
meant that there are now more organisations
looking to back wind farm projects than there
are projects, and the financing market has
therefore become more competitive. This has
given more power to the turbine suppliers and
wind farm developers, and resulted in lenders
accepting more risk in their financing structures.
For example:
In some cases, lenders are providing finance
to projects or portfolios where not all the consents
are in place, but a turbine supply contract
has been agreed. This may initially seem risky,
but is based on the sound premise that the turbine
supply agreement is a valuable asset.
Should the project itself fail to reach construction,
then the turbines can be sold on to
recoup the debt.
Lenders have become more comfortable
with financing projects that are constructed on
a multi-contract basis, driven by the turbine
shortage, as turbine suppliers are concentrating
on producing turbines and are less inclined
to take the risk associated with taking on the
balance of plant work associated with wind
farm projects.
Lenders are having to accept shorter warranties
in turbine contracts, with two years
now typical. Again, this is driven by the high
demand for turbines giving the upper hand to
turbine suppliers.
Developers are increasingly turning to smaller,
less experienced turbine manufacturers to
meet their development goals. While the
expansion of the turbine market can only be a
good thing in the longer term, in the short
term, equity and debt providers are having to
quantify the increased technical risks associated
with less well-proven technologies.
Developers are increasingly pushing lenders
towards financing projects without a long-term
PPA. From a developer’s perspective, long term
PPAs are becoming less attractive as they are
losing out on the upside of increasing electricity
prices. They would rather take their chances
on a buoyant market with the prospect of significantly
increasing their profitability. The
lenders, of course, have little interest in the
upside, but are being driven towards accepting
this higher risk approach.
More creative financing structures are being
applied, including the use of mezzanine financing
to allow higher debt ratios and the profiling
of debt repayment to minimise the risk of ‘merchant
tails’ (revenue risk beyond the end of
PPAs). Hedging – of fluctuations in the electricity
price, or of the wind resource itself – is also
being incorporated into some financing structures
to offset risks.
Lenders are keen to look at financing portfolios
of wind farm projects, to benefit from
economies of scale and risk diversification,
preferably in different wind regimes and with
different turbine technologies. If a portfolio is
situated across different countries then all the
better – this spreads risk across different legislations
and wind support mechanisms as well.
Finally, what about the impact of the credit
crunch? Is the wind industry suffering from a
more cautious approach to debt? The jury is
still out. Some argue that a lack of easy finance
will have a negative impact on the industry,
while others suggest that many investors will
turn to the electricity sector as a safe haven in
turbulent times. Whatever the theories, our
experience is that the wind industry is still
going strong.
Richard Boddington is wind analysis manager and
Simon Luby is due diligence team leader at consultancy
SgurrEnergy, based in Glasgow, Scotland.
|